LINKEDINCOMMENTMORE

The Zoo interchange will be closed overnight March 28 and 29.

The Wisconsin Department of Transportation’s Zoo Interchange team will be completing deck pours on the new Wisconsin Avenue bridge and on the new ramp from eastbound Interstate-94 eastbound to northbound Interstate-41 during overnight hours March 28 and 29. No specific time is set for the work due to varying construction schedules.

The work being accomplished is a major step in the completion of the new bridge and system ramp, according to the DOT.  Both structures are targeted for late spring openings, with efforts to have both open by the Memorial Day weekend.

Detours and additional information is available at projects.511wi.gov/zoo-interchange-project.

Read or Share this story: http://www.wauwatosanow.com/story/news/2017/03/28/zoo-interchange-work-cause-shutdowns/99744224/